Project Stats
Client
Towne Properties
Location Cincinnati, OH
Year
2015
Market
Size 20 000.00 sq ft - Building Pad

Services Provided:

    • SURVEYING SERVICES
    • CIVIL ENGINEERING SERVICES
    • LANDSCAPE ARCHITECTURE & PLANNING SERVICES
  • SURVEYING SERVICES

    • Boundary Surveys
    • Construction Layout & Staking
    • Topographic Surveys
  • CIVIL ENGINEERING SERVICES

    • Earth Retaining Structures
    • Erosion Control Planning, Permitting & Inspection
    • Foundation Design
    • Grading & Earthwork Analysis
    • Storm Water Collection System
    • Structural Site Amenities
  • LANDSCAPE ARCHITECTURE & PLANNING SERVICES

    • Community and Urban Design
    • Irrigation Plans
    • Lighting Plans

Interested in learning more?

Contact Us Now

Project Highlight

A fixture and landmark of Mount Adams throughout the history of Cincinnati, Holy Cross Monastery and Church underwent a significant renovation and evolution in use in late 2014. Given the unique location and site challenges, Bayer Becker was selected to provide surveying, civil engineering, construction documentation, construction administration and project management services by Towne Properties. In addition to the venue’s new use as an event space, the facility also includes Towne Properties’ corporate office which was renovated simultaneously. The Bayer Becker team collaborated with landscape architect and garden designer, Human Nature, along with Herndon Engineering (MEP), Towne Properties (Construction Manager/Client) and Townescapes (contractor) to compliment the historic landmark with engaging garden space. Bayer Becker was responsible for ensuring that there were clear lines of communication between all parties involved, that the quality of the installation met expectations, and challenges in the field were being addressed creatively and efficiently.

Bayer Becker first prepared the topographic survey, which served as the base for design drawings, provided the layout, grading plan, and storm water management plans for the garden based upon the design provided by Human Nature. Additionally, Bayer Becker provided construction details including sections and elevations of the ramp, steps, seat walls and paving all the while ensuring collaboration between the design and construction team.

The renovation took place between the winter months of November 2014 and May 2015, requiring an extremely demanding schedule. As project manager, Bayer Becker leveraged its relationship and previous teaming experience with the client and the construction manager to work through any design challenges encountered during the renovation. Bayer Becker also assisted with permitting for the garden and event tents. By recording and organizing RFI correspondence, monitoring the quality of the executed work, and working together with the appropriate entities through construction, Bayer Becker was a critical factor in completing the project on time.

Bayer Becker’s engineering, surveying, construction documentation and construction management services were all leveraged during the project to provide technical drawings that supported the vision for the garden’s design.  Our attention to detail during each stage proved to be extremely valuable to the successful completion of the project in time for the first wedding at the Chapel Garden.

Get In Touch With Us

  • CINCINNATI   (513) 834-6151
    1404 Race Street Suite 204
    Cincinnati, Ohio  45202
  • INDIANAPOLIS   (317) 207-1979
    1060 North Capitol Ave Office 15
    Indianapolis, IN  46204
  • MASON   (513) 336-6600
    6900 Tylersville Road Suite A
    Mason, Ohio  45040
  • NORTHERN KENTUCKY   (859) 261-1113
    209 Grandview Drive
    Fort Mitchell, Kentucky  41017
  • OXFORD   (513) 523-4270
    110 South College Avenue Suite 101
    Oxford, Ohio  45056